Some good 
news: the repair of the weir and bankside is going to go ahead and EA permissions 
are being sought for the works currently. The anticipated time scale is as 
follows:
- 
End of March – submit Methodology incl. measures to address pollution risks, silk risks, flood risks, daily EA flood alerts.
 - 
End of April – Flood Defence Consent approval.
 - 
Mid-May – commence works.
 - 
Mid-June – complete works.
 
Following the works there will need to be additional soft landscaping and 
planting which Ladywell Fields User Group may contribute to.