Repairs to River Ravensbourne Weir

Some good news: the repair of the weir and bankside is going to go ahead and EA permissions are being sought for the works currently. The anticipated time scale is as follows:
  • End of March – submit Methodology incl. measures to address pollution risks, silk risks, flood risks, daily EA flood alerts.
  • End of April – Flood Defence Consent approval.
  • Mid-May – commence works.
  • Mid-June – complete works.
Following the works there will need to be additional soft landscaping and planting which Ladywell Fields User Group may contribute to.